HUSH were appointed for the design and construction of the second phase of a wider development on Millington Road. The development comprises two industrial units; The scheme was designed to RIBA Stage 3/4 taking into consideration the tenants specific requirements whilst not compromising on future lettability. Planning submitted for the site and consented in September 2016 subject to completion of the S106. The scheme was procured through a design and build contract with works completed in July 2017. |
Client
BSPF
Building/Street Name
Millington Road, Hayes
Area
45,000 sq. ft
Construction Period
32 weeks